According to the approved investment program of VAT Volynoblenergo, in 2004 the enterprise plans to invest 250 thousand hryvnias in the installation of 10 unloading substations of 6-10 kV. The main reason why the completion of 10 such substations is needed is that the voltage level for consumers connected at the end of such transformer points (TP) is 12-15 percent below the norm, as well as significant electricity losses. As a result of the construction in 2004 of 10 unloading TPs of 10/0.4 kV, for which 250 thousand hryvnias are planned to be spent, in the places where their installation is planned, it has been calculated that the reduction of losses per 1 TP will amount to 9.8 thousand kWh/year. The payback period of the investment intentions is 21 years. Reference: In the facilities of VAT Volynoblenergo, 85 TPs of 6-10/0.4 kV are currently in operation, from which the length of the main line of an individual 0.4 kV overhead line exceeds 3.5 km.